Short answer (14 Nov 2026): Neither the Beawar–Bharatpur nor the Jaipur–Pachpadra expressway is reported to be under construction. In the reports we reviewed, the stage is land acquisition. For Beawar–Bharatpur, a Jaipur district order reported in November 2025 prohibited sale and purchase of land in 24 villages of Phagi and Madhorajpura tehsils. NHAI is building Jaipur–Pachpadra and was reported to have been asked to speed up land acquisition.
Last updated 14 Nov 2026. Figures are from news reports and shown with their dates. Alignments, lengths and village lists are not final.
Latest update log
- 25 May 2026: The Rajasthan State Road Development Corporation board approved a Rs 4,938 crore loan for land acquisition for the Kotputli–Kishangarh and Beawar–Bharatpur expressways. NBM&CW.
- Late 2025: Patrika reported the Chief Minister’s review: NHAI should start land acquisition for the proposed greenfield expressways soon. The article lists nine proposed expressways and says Beawar–Bharatpur was cut from 342 km to 270 km, now Bharatpur to near Bagru. The page shows a display date of 28 October 2026 while the article timestamp reads 28 November 2025, so we treat the report as late 2025. Patrika.
- 6 Nov 2025: Patrika reported that District Collector Jitendra Kumar Soni’s letter to SDMs and tehsildars prohibited sale and purchase of land in 24 villages of Phagi and Madhorajpura tehsils for the Beawar–Bharatpur corridor. Patrika.
- 11 Jul 2025: NHAI was reported to take over construction of the Jaipur–Pachpadra and Bikaner–Kotputli expressways, earlier proposed by a state agency. NBM&CW.
The two corridors side by side
| Beawar–Bharatpur | Jaipur–Pachpadra | |
|---|---|---|
| Length reported | 342 km (Nov 2025); later reported as 270 km, Bharatpur to near Bagru | About 350 km |
| Who is building | State; the RSRDC loan of 25 May 2026 covers its land acquisition | NHAI, after the July 2025 takeover |
| Cost reported | Not stated in the reports we reviewed | Estimated Rs 11,492 crore (July 2025) |
| Jaipur district impact reported | 24 villages, Phagi and Madhorajpura tehsils, sale and purchase prohibited | Passes through Kishangarh, Ajmer and Jodhpur; the Jaipur alignment was not described |
| Other districts named | Ajmer, Tonk, Dausa, Sawai Madhopur | Not stated |
| Stage in reports | Land acquisition preparation | NHAI asked to speed up land acquisition |
Why the Beawar–Bharatpur length differs
The 342 km figure appears in the November 2025 Patrika report. The later review report says the length was cut to 270 km and the corridor now runs from Bharatpur to near Bagru. We cannot tell from the reports which alignment the 24-village ban was written for, so a buyer should not assume that a village outside the 24 is safe. Treat both figures as reported, and check the village at the tehsil.
What it means if you are looking at land near Phagi, Madhorajpura or Bagru
- Ask for the village list in writing. The report did not name the 24 villages or give the order date or duration. Get the current order from the Phagi or Madhorajpura tehsil before any advance.
- Do not assume registry is open. The report mentions sale, purchase and conversion, not deed registration. Ask the sub-registrar.
- “Expressway-touch” pricing is a claim, not a fact. No alignment map for the Jaipur section was published in the reports we reviewed. Which of Rajasthan’s nine expressways matter for Jaipur land.
- Verify the khasra. Check the jamabandi for acquisition remarks and the exact khasra against any notification. How to read khasra, khata and jamabandi.
Frequently asked questions
Which Jaipur villages are restricted?
24 villages of Phagi and Madhorajpura tehsils were reported in November 2025. The villages were not named in the report.
Has construction started?
We found no report of construction start on either corridor. The stage reported is land acquisition.
Who builds Jaipur–Pachpadra?
NHAI, per the July 2025 report.
Can I buy farmland near these corridors?
Only after checking the exact khasra against acquisition lists and sale restrictions at the tehsil.
Sources
- Patrika, 6 Nov 2025: Land transactions halted in 24 Jaipur villages
- Patrika: CM directs land acquisition for greenfield expressways
- NBM&CW, 25 May 2026: RSRDC approves Rs 4,938 crore loan
- NBM&CW, 11 Jul 2025: NHAI to build Jaipur–Pachpadra and Bikaner–Kotputli
General information from published reports, not legal advice. Confirm with the tehsil and a local advocate before you pay.